Bayview Services was contracted by The Whiting-Turner Contracting Company for the SOF-X Treehouse project after significant water intrusion impacted a newly constructed six-story building. Originally awarded as a small $35,000 concrete block removal project, the scope rapidly expanded into a large-scale demolition, environmental remediation, and water damage recovery effort valued at approximately $3,000,000.

As concerns regarding potential mold contamination increased throughout the building, Bayview Demolition and Bayview Environmental worked together to perform comprehensive demolition, cleanup, and abatement services across approximately 120,000 square feet of affected areas. The project required extensive coordination, rapid mobilization, and aggressive scheduling to mitigate damage and support the recovery of the structure.

At peak production, Bayview managed a workforce of approximately 80 personnel on-site. Superintendent Art Alfaro played a critical role in organizing field operations, coordinating manpower, and securing the equipment and materials necessary to successfully execute the project. Foreman Juan Lopez and the field team worked closely with project stakeholders to ensure all demolition and remediation activities were completed safely, efficiently, and in compliance with project requirements.

The project was completed between January 9, 2026, and May 15, 2026, achieving a 75% material diversion rate while maintaining Bayview’s commitment to quality, safety, and environmental responsibility throughout all phases of work.

Key Metrics

Diversion

75%

Similar Projects
Employee Portal

Our Website uses cookies. Cookies are small text files held on your computer that help us understand how you use our Website. Our cookies do not store any personal information about you, and you can delete and block cookies via your browser settings at any time. By clicking “Ok” you agree to accept our use of cookies. Learn more by reviewing our privacy policy.