Project Summary
On this project, Bayview deployed its Demolition and Environmental divisions in order to complete the scope. The historical Graduate Hotel of Palo Alto California was to receive a full gut on every one of its six 7,500 square foot floors, as well as its roof and basement. The Environmental team abated all of the lead and asbestos materials throughout the building. Offload was a challenge on this project. With no area on the street for dumpsters, the dumpsters had to be brought into the ground floor of the building. Once the building has passed clearance, the Demolition team will move in and complete the soft demolition and selective hard demolition at various locations of the site.