bayviewservices.com

Project Updates

  • Bayview Demolition
  • Bayview Environmental
300 Clay Street
San Francisco
Project Summary

This project is about 40,000 SF contaminated fireproofing and combined with non-hazardous demolition. We went over the completion date because with have a lot of challenges , such as MEP’s not being properly safed off and the other challenges was using an small elevator to offload about 30,000 pounds of material. Overall the project turned out great and the client was happy.

View Project
Team
  • Superintendent Jesus Delgado
  • Foreman Javier Solis
  • Bayview Environmental
41 Tunnel Road
Berkeley
Project Summary

The project is about 50,000 SF of roofing material with a high pitch roof about 100 feet high. Our crew needed to work off a scaffold and  hang from the pitch of the roof with harnesses to remove the upper portion.  Additional protection was necessary to prevent falling debris due to this being an active campus with pedestrians walking around the premises. This project will go over three phases and be completed on summer of 2026.

View Project
Team
  • Superintendent Geronimo Valenzuela
  • Foreman Oscar Avalos
  • Bayview Environmental
Fullerton College Building 300
Fullerton
Project Summary

Bayview Environmental services was contracted to complete the renovations of the 20,000 SF Building 300 at Fullerton College. Building 300 is the first building built on this campus and is considered culturally and historically significant. The scope of work included the abatement and demolition of interior finishes while protecting historical components in place. The abatement included removal and disposal of asbestos containing and lead materials; floor tile, mastic, tsi insulation, chalk board mastic, and chalk board rails. The selective demolition consisted of removal and disposal of interior plaster walls, ceiling systems, MEP’s, flooring, & light fixtures. Structural demolition consisted of new openings throughout the 1st and 2nd floor deck as needed for new mechanical ducts and installation of piles. Bayview team also selectively demolished exterior staircases for the installation of piles.

View Project
Team
  • Superintendent Patrick Marmaud
  • Foreman Juan Ibarra
  • Bayview Demolition
SDG&E Headquarters
San Diego
Project Summary

Bayview Demolition Services was awarded the interior demolition of SDG&E CP4.2 2nd floor tenant improvement. Bayview was tasked to provide a full interior gut of the 39,000 SF 2nd floor. This included partition walls, flooring, ceilings, and MEP’s. Demolition also included removal and disposal of concrete deck and framing for new structural upgrades at multiple locations throughout the 2nd floor. Bayview completed the project in accordance with SDG&E’S LEED requirements which included diverting 4 types of construction debris from the landfill.

View Project
Team
  • Superintendent Jose Torres
  • Foreman Ruben Alcocer