bayviewservices.com

Project Updates

  • Bayview Demolition
311-333 Airport Blvd
San Francisco, Ca
Project Summary

Bayview Demolition was tasked with cutting new shafts and elevator openings in two new buildings at 311 Airport Blvd. Each building had 9 levels which required saw-cutting, concrete removal, and demolition of pan decking at multiple shafts and elevator openings. Material movement constraints and a tight schedule were managed to make this project a success.

View Project
  • Bayview Demolition
  • Bayview Environmental
USD Camino & Founders Hall
San Diego
Project Summary

This project took place on an active campus within two historic buildings at the University of San Diego. Bayview performed the abatement of all asbestos and lead containing materials, as well as the interior and exterior soft and hard demolition. There were many challenges that the project team had to navigate, in addition the sequencing, fast paced schedule, and continuous concurrent work areas/containments, this project began in the early stages of the pandemic, nonetheless it was another successful project.

View Project
  • Bayview Environmental
  • Bayview Industrial
Lehigh Hanson – Golden Arrow
Stockton, CA
Project Summary

Bayview was brought into this project to assist Lehigh Hansen with the removal of approximately 130K of HFO from Main and double bottom tanks on board the Golden Arrow. The defuel operations were part of a reclassification of the vessel. HFO was pre-heated with temporary boiler systems and transferred ship to shore under the Bayview over water transfer notification system. The fuel was then shipped off site to a pre-determined reclamation facility. The project was completed in the projected time line and on budget.

View Project