Project Summary
This was a multifaceted remediation project that included laboratory decontamination, hazardous material abatement of Asbestos, Lead and PCBs as well as soft demolition. Bayview Environmental Services ultimately cleared both buildings of all impacted materials to prepare it for complete demolition by Ferma Corp.
The remediation scope included the precleaning and decontamination of all lab space, counter tops, fume hoods and ventilation systems, the removal of asbestos containing fireproofing, drywall and joint compound, flooring, and associated mastics as well as the removal of PCB impacted ballasts, caulking and other impacted substrates. This was a unique project that was completed under the challenging and ever evolving COVID -19 social distancing requirements and protocols.