Project Summary
The Boykin Hall Project, located on the Santa Clara Community College campus, showcased Bayview’s precision in managing complex interior and exterior demolition within an active educational environment. The selective demolition scope included the removal of existing casework, doors and frames, exterior wall tile, flooring, ceilings, MEP systems, lighting tubes and ballasts, and other building finishes across the first through third floors, as well as the roof. With a consistent crew of 8–10 team members over a four-month duration, Bayview successfully completed the $200,000 contract safely, efficiently, and on schedule.